Tuesday, 10 March 2015

Limiting Factors

What is a limiting factor?
A limiting factor is a factor that prevents a company from achieving the level of activity that it would like to. Uses the contribution concept to solve the allocation of scarce resources.
Scarce resources maybe one or more manufacturing inputs (material, labor, machine time) needed to make a product and in short supply (the resource i.e.). Production can also be affected by demand or sales.

Example 1:
Suppose A Ltd makes two products, X and Y. Both products use the same machine and the same raw material that are limited to 200 hours and $500 per week respectively. Individual product details are as follows:

Product X per unit
Product Y per unit
Machine hours
5.0
2.5
Materials
$10
$5
Contribution
$20
$15
Maximum weekly demand
50 units
100 units
Required:
Identify the limiting factor.

 Example 2
Two products, alpha and Gamma are made of Material X and require skilled labor in the production process. The product details are as follows:

Alpha $

Gamma $
Selling price
10.00

15.00
Variable cost
6.00

7.50
Contribution
4.00

7.50




Material X required per unit
2 kg

4 kg
Skilled labor time required per unit
1 hour

3 hours
The maximum demand per week is 30 units of Alpha and 10 units of Gamma. The company can sell all the Alphas and Gammas that it can make but there is a restriction on the availability of both Material X and skilled labor. There are 150 kg of material, and 45 hours of skilled labor, available per week.
Required:
Identify the limiting factor.

Contribution per unit of limiting factor
In order to decide order of production, the contribution per unit of limiting factor will have to be calculated. The following illustrate the steps:

A Ltd makes products X and Y using the same machine and raw materials. Machine hours are limited to 200 hours and materials $500 per week respectively. Details:


Product X per unit
Product Y per unit
Machine hours
5.0
2.5
Materials
$10
$5
Contribution
$20
$15

As there are two possible limiting factors, a test will be necessary if one or both are. You can only apply these steps on one limiting factor situations. In this case, say machine hours is the limiting factor. The following is then calculated:

Contribution per unit of limiting factor
=
Contribution per unit
Units of limiting factor required per unit

Product X
$20 / 5 hours
=
$4 per machine hour
Product Y
$15/2.5 hours
=
$6 per machines hour

Product Y has a higher contribution per unit of limiting factor (machine hours) so it should be made first. The balance of machine hours would then be assigned to Product X.

Optimal production plan
When limiting factors are present, the objective is to maximize contribution  (which in turn maximize profits) by producing products in the order of the highest amount of contribution per unit of limiting factor. The profit maximizing production mix is known as the optimal production plan. Steps:
1)    Calculate the contribution per unit of product.
2)    Calculate the contribution per unit of limiting factor (scarce resource)
3)    Rank products
4)    All the scarce resource to the highest ranked products.
5)    Once demand for highest ranked products is satisfied, move on to the next highest ranking product, repeat until the resource is used up.
Example 1
A company is able to produce four products and is planning its production mix for the following period. Relevant data is given below:

A
B
C
D
Selling price ($) per unit
19
25
40
50
Labor cost per unit ($)
6
12
18
24
Material cost per unit ($)
9
9
15
16
Maximum demand (units)
1,000
5,000
4,000
2,000
Labor is paid $6 per hour and labor hours are limited to 12,000 hours in the period.
Required:
Determine the optimal production plan and calculate the total contribution it earns for the company.
Example 2
The following data relates to Products Able and Baker.


Product


Able
Baker
Direct materials per unit

$10
$30
Direct labor:



     Grinding
$5 per hour
7 hours per unit
5 hours per unit
     Finishing
$7.50 per hour
15 hours per unit
9 hours per unit
Selling price per unit

$206.50
$168.00
Budgeted production

1,200 units
600 units
Maximum sales for the period

1,500 units
800 units
Notes:
1)    No opening or closing inventory anticipated
2)    The skilled labor used for the grinding processes is highly specialized and in short supply, although there is just sufficient to meet the budgeted production. However, it will not be possible to increase the supply for the budget period.
Required:                                                             
Determine the optimal production plan and calculate the total contribution it earns for the company.
    
 Linear programming
The optimal production plan is only applicable to situations with only limiting factor. When there are more than one limiting factor, then a technique known as linear programming is used.

Formulating a linear programming problem
The steps involved are as follows:
1)    Define the unknowns, i.e. the variables that need to be determined.
2)    Formulate the constraints, i.e. the limitations that must be placed on the variables.
3)    Formulate the objective function that needs to be maximized or minimized.
Note that non-negativity constraints will be needed to ensure that there are no negative values.

Example 1
A company makes two products, X and Y, and wishes to maximize profit. Information on X and Y is as follows: 

Product X

Product Y
Material kg per unit
1

1
Labor hours per unit
5

10

$

$
Selling price per unit
80

100
Variable cost per unit
50

50
Contribution per unit
30

50
The company can sell any number of product X, but expects the maximum annual demand for Y to be 1,500 units. Labor is limited to 20,000 hours and materials to 3,000 kg p.a. 
Required:
Using the information given, formulate the linear programming problem.
  
Example 2
A builder has purchased 21,000 m² of land on which it is planned to build two types of dwelling, detached and town houses, within an overall budget of $2.1 million. A detached costs $35,000 to build and requires 600 m² of land. A town house costs $60,000 to build and requires 300 m² of land. To comply with local planning regulations, not more than 40 buildings may be constructed on this land, but there must be at least 5 of each type. From past experience the builder estimates the contribution on the detached house to be about $10,000 and on the town house to be about $6,000. Contribution is to be maximized.
Required:
Using the information given, formulate the linear programming problem.

It is possible to solve to solve linear programming problems with two variables by drawing a graph of the constraint and the objective function. Steps involved:
1)    Define the unknowns, i.e. the variables that need to be determined.
2)    Formulate the constraints, i.e. the limitations that must be placed on the variables.
3)    Formulate the objective function (that needs to be maximized or minimized).
4)    Graph the constraints and objective functions.
5)    Determine the optimal solution to the problem by reading the graph.

Example 1
The constraints and the objective function of a linear programming problem concerning how many units of products X and Y to be produced and sold each year have been formulated to be as follows: 
Constraints
Materials
x + y
3,000
Labor hours
5x  + 10y
20,000
Maximum sales
y
1,500
Non-negativity
x
0

y
0
The objective function is to maximize 30X + 50y where: 
x
=
number of units of X produced and sold each year
y
=
number of units of Y produced and sold each year
Required:
Determine the optimal solution to this linear programming problem using a graphical approach.

Example 2
The constraints and the objective function of a linear programming problem concerning how many detached houses and town houses to be built have been formulated to be as follows:
Constraints
Area
600x + 300y
21,000
Costs
35x  + 60y
2,100 (in $000)
Number
x + y
40
Minimum
x
5

y
5
Non-negativity
x
0

y
0
The objective function is to maximize 10X + 6y where: 
x
=
number of detached houses
y
=
number of town houses
Required:
Determine the optimal solution to this linear programming problem using a graphical approach. (Note: do not draw the iso-contribution line in order to determine the optimal solution.)
  
Using equations to solve linear programming problems
Equations can be used to determine where the two lines cross.

For e.g., in example 1, we established that the optimal solution was at Point C using the graphical method. Point C represents the point at which the sales constraint intersects the labor constraint.

Labor constraint
5x + 10y
=
20,000
(1)
Materials constraint
x + y
=
3,000
(2)

The basic method is to eliminate one of the two unknowns between the equations. This is achieved by adding or subtracting the equations. This is known as solving simultaneous equations.

Example 1
Solve the following simultaneous equations.

5x + 10y
=
20,000
(1)
x + y
=
3,000
(2)
  

Example 2
Suppose that the optimal solution to a linear programming problem is at the intersection of the following two constraint lines:

2x + 3y
=
1,700
 (1)
5x + 2y
=
2,600
 (2)

Required:
Determine the values of x and y using simultaneous equations.
  
Establishing the optimal solution using simultaneous equations
Using simultaneous equations should be done with caution:
·         It is not recommended that you solve sets of simultaneous equations until you have determined graphically which constraints are effective in determining the optimal solution.
·         Solutions using graphical method relies on graphs being drawn clearly so accurate readings may be taken.
·         If it is not easy to read the coordinates of the required points from a graph then the simultaneous equations provides a reliable check.

Example 3
Alfred Ltd is preparing its plan for the coming month. It manufactures two products, the Flaktrap and the Saptrap. Details are as follows: 

Product


Flaktrap
Saptrap
Price/wage rate
Selling price ($)
125
165

Raw materials (kg)
6
4
$5/kg
Labor hours



     Skilled
10
10
$3/hour
     Semi-skilled
5
25
$3/hour
The company's variable OAR is $1 per labor hour (for both skilled and semi skilled labor). The supply of skilled labor is limited to 2,000 hours per month and the supply of semi-skilled labor is limited to 2,500 hours per month. 
At the selling prices indicated, maximum demand for Flaxtraps is expected to be 150 units per month and the maximum demand for Saptraps is expected to be 80 units per month.
Required:
Use simultaneous equations to solve the linear programming problem given above.



No comments:

Post a Comment